Paving List
Newton County paves more than 20 miles of roads a year.
Paving and resurfacing is done in coordination with the Georgia Department of Transportation's (GDOT) Local Maintenance Improvement Grant (LMIG).
The LMIG paving for 2023 is underway.
See interactive Paving Map here
2023 LMIG Project List
Road Name | Beginning | Ending | Length (Miles) | Description of Work | District | Status |
---|---|---|---|---|---|---|
Brittney Lane | Rocky Plains Rd | Cul De Sac | .32 | Patch and Resurface | 1 | COMPLETED June 23 |
Brookhollow Way | Loyd Rd | Cul De Sac | .53 | Patch and Resurface | 1 | COMPLETED April 23 |
Spring Ct | Brookhollow Way | Cul De Sac | .17 | Patch and Resurface | 1 | COMPLETED April 23 |
Willow Dr. | Willow Wood Rd | Adams Circle | .21 | Patch and Resurface | 1 | COMPLETED April 23 |
Dukes Rd. | Gaithers Rd. | S.R. 11 | 1.30 | Patch and Resurface | 1 | COMPLETED March 23 |
West Forest Dr. | Oaks Hill West | Cul De Sac | .35 | Patch and Resurface | 2 | COMPLETED Feb. 23 |
Oak Hill West | S.R. 20 | S.R. 212 | .37 | Patch and Resurface | 2 | COMPLETED Feb. 23 |
Stone Creek Dr. | S.R. 20 | Cul De Sac | .19 | Patch and Resurface | 2 | COMPLETED March 23 |
Pebble Blvd. | No. 485 | No. 795/760 | .48 | Patch and Resurface | 2 | COMPLETED Aug. 23 |
Pebble Brooke Pass | No. 195 | Pebble Blvd. | .29 | Patch and Resurface | 2 | COMPLETED Aug. 23 |
Woodland Rd. | Brown Bridge Rd. | Forest Rd. | .22 | Patch and Resurface | 2 | COMPLETED Aug. 23 |
Coldwater Dr. | Hwy. 212 | Cul De Sac | .5 | Patch and Resurface | 2 | COMPLETED |
Carmel Dr. | Coldwater Dr. | Cul De Sac | .11 | Patch and Resurface | 2 | COMPLETED |
Coldwater Way | Coldwater Dr. | Cul De Sac | .16 | Patch and Resurface | 2 | COMPLETED |
Valley View Rd. | Bailey Creek Rd. | Rockdale County Line | .12 | Patch and Resurface | 2 | COMPLETED Feb. 23 |
Kent Rock Rd. | S..R. 138 | Walton County Line | .79 | Patch and Resurface | 3 | COMPLETED April 23 |
Natalie Ct. | Jack Neely Rd. | Sammy Ct. | .18 | Patch and Resurface | 3 | COMPLETED July 23 |
Bowen Way | Natalie Ct. | Cul De Sac | .34 | Patch and Resurface | 3 | COMPLETED July 23 |
Cherohala Ct. | Bowen Way | Cul De Sac | .21 | Patch and Resurface | 3 | COMPLETED July 23 |
Suzy Ct. | Bowen Way | Cul De Sac | .05 | Patch and Resurface | 3 | COMPLETED July 23 |
Carriage Park Ct. | Bald Rock Rd. | Cul De Sac | .28 | Patch and Resurface | 3 | COMPLETED May 23 |
Doubles Dr. | Brown Bridge Rd. | Cul De Sac | .45 | Patch and Resurface | 3 | COMPLETED Aug. 23 |
Rodney Way | Doubles Dr. | Cul De Sac | .23 | Patch and Resurface | 3 | COMPLETED Aug. 23 |
Roseberry Ct. | Old Atlanta Hwy. | Cul De Sac | .05 | Patch and Resurface | 4 | COMPLETED Aug. 23 |
East Dollar Cir. | 1-20 Access Rd. | End | .47 | Patch and Resurface | 4 | COMPLETED May 23 |
Hegwood Dr. | S.R. 81 S | End | .13 | Patch and Resurface | 4 | COMPLETED June 23 |
Whitehead Dr. | Mote Rd. | Cul De Sac | .42 | Patch and Resurface | 4 | COMPLETED June 23 |
Whitehead Ct. | Whitehead Dr. | Cul De Sac | .10 | Patch and Resurface | 4 | COMPLETED June 23 |
Highwood Dr. | Fire Tower Rd. | Cul De Sac | .38 | Patch and Resurface | 4 | COMPLETED June 23 |
Fernwood Ct. | Highwood Dr. | Cul De Sac | .04 | Patch and Resurface | 4 | COMPLETED June 23 |
Wayland Ct. | Highwood Dr. | Cul De Sac | .03 | Patch and Resurface | 4 | COMPLETED June 23 |
Beachwood Ct. | Highwood Dr. | Cul De Sac | .04 | Patch and Resurface | 4 | COMPLETED June 23 |
Auburn Ct. | Highwood Dr. | Cul De Sac | .09 | Patch and Resurface | 4 | COMPLETED June 23 |
Byrd Rd. | W. Macedonia Church Rd. | Gum Creek Rd. | 1.24 | Patch and Resurface | 5,3 | COMPLETED May 23 |
Mount Tabor Rd. | Sockwell | Dirt | .98 | Patch and Resurface | 5 | COMPLETED May 23 |
Geoffrey Ln. | Ellington Rd. | Walton County Line | .48 | Patch and Resurface | 5 | COMPLETED May 23 |